Back to projects

Rehabilitation of tracks on the Montréal & Ottawa subdivision

Vaudreuil-Dorion, Quebec

completePublic TransitPTIF
Federal contribution
$1.0M
$1,024,425
Federal share50%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 13, 2017
2017201820192020
Built

Approved 5 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Apr 1, 2016(actual)
Construction end
Nov 30, 2019(actual)

Also in Vaudreuil-Dorion

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50304 in the federal list. How to read these figures.