Bearspaw Trail Construction
Federal contribution
$50,000
Federal share15%
of $341.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2016
2016
Built
Approved 13 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Glenbow Ranch Park Foundation
- Construction start
- Jul 15, 2015(actual)
- Construction end
- Nov 5, 2015(actual)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50422 in the federal list. How to read these figures.