Back to projects

West Bragg All Season Trail Plan Implementation

Bragg Creek, Alberta

completeRecreationNRT
Federal contribution
$26,000
Federal share26%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2016
2016
Built

Approved 13 months before the announcement.

Program
National Recreational Trails Program
Construction start
May 15, 2015(actual)
Construction end
Nov 13, 2015(actual)

Also in Bragg Creek

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50426 in the federal list. How to read these figures.