Trans-Québec Trail 396 Maintenace between Matagami and Lebel-sur-Quévillon

Matagami, Quebec

completeRecreationNRT
Federal contribution
$81,178
Federal share50%

of $162.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 30, 2009
2010
Built

Approved 2 months before the announcement.

Program
National Recreational Trails Program
Ultimate recipient
Club Motoneige Matagami
Construction start
May 26, 2009(actual)
Construction end
Mar 31, 2010(actual)