Culvert and Staging Area
Federal contribution
$5,000
Federal share50%
of $10.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2016
2016
Built
Approved 9 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Woodridge ATV Sandhogs Inc.
- Construction start
- Jul 2, 2015(actual)
- Construction end
- Dec 30, 2015(actual)
Also in La Broquerie
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50591 in the federal list. How to read these figures.