Goose Lake Reconnection
Federal contribution
$10,000
Federal share31%
of $32.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2016
2016
Built
Approved 13 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Crocus Trail
- Construction start
- Feb 18, 2015(actual)
- Construction end
- Dec 30, 2015(actual)