Back to projects

Falcon Bridge Trails Improvement

Falcon Lake, Manitoba

completeRecreationNRT
Federal contribution
$3,846
Federal share26%

of $15.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2016
2016
Built

Approved 11 months before the announcement.

Program
National Recreational Trails Program
Construction start
Jul 6, 2015(actual)
Construction end
Dec 30, 2015(actual)

Also in Falcon Lake

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50605 in the federal list. How to read these figures.