Five Bridge Lakes Wilderness Area
St. Margarets Bay, Nova Scotia
Federal contribution
$31,721
Federal share50%
of $63.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2016
20152016
Built
Approved 17 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Safety Minded ATV Association
- Construction start
- Nov 8, 2014(actual)
- Construction end
- Dec 30, 2015(actual)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50687 in the federal list. How to read these figures.