Announced and approvedMar 31, 2016
2016
Built
Approved 13 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Bay to Bay Trail Association
- Construction start
- Mar 31, 2015(actual)
- Construction end
- Dec 4, 2015(actual)