Back to projects

Adventure Trail Upgrade

Blockhouse, Nova Scotia

completeRecreationNRT
Federal contribution
$11,985
Federal share26%

of $46.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2016
20152016
Built

Approved 18 months before the announcement.

Program
National Recreational Trails Program
Ultimate recipient
Adventure Trail Association
Construction start
Oct 1, 2014(actual)
Construction end
Dec 11, 2015(actual)

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50707 in the federal list. How to read these figures.