Johnstown ATV Club Supported Trail Improv. & Upgrade
Federal contribution
$8,931
Federal share50%
of $17.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2016
20152016
Built
Approved 16 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Johnstown ATV Club Inc.
- Construction start
- Dec 6, 2014(actual)
- Construction end
- Oct 16, 2015(actual)