Limerick Forest Trail Network Rehabilitation, Upgrading and Signage
Federal contribution
$21,000
Federal share49%
of $42.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2016
20152016
Built
Approved 15 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Bytown Motorcycle Association: BMA
- Construction start
- Jan 5, 2015(actual)
- Construction end
- Nov 30, 2015(actual)
Also in Kanata