Back to projects

Limestone trail covering north of Bobcaygeon

Lindsay, Ontario

completeRecreationNRT
Federal contribution
$55,166
Federal share50%

of $110.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2016
20152016
Built

Approved 16 months before the announcement.

Program
National Recreational Trails Program
Construction start
Nov 20, 2014(actual)
Construction end
May 26, 2015(actual)