Trail Development
Federal contribution
$60,097
Federal share17%
of $348.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2016
2016
Built
Approved 13 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Prince Edward Island Snowmobile Association
- Construction start
- Jul 6, 2015(actual)
- Construction end
- Oct 14, 2015(actual)
Also in Winsloe