Back to projects

Ste-Sophie interregional cycle path towards la route verte (Parc linéaire)

Sainte-Sophie, Quebec

completeRecreationNRT
Federal contribution
$50,000
Federal share22%

of $225.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2016
2016
Built

Approved 10 months before the announcement.

Program
National Recreational Trails Program
Construction start
Jul 1, 2015(actual)
Construction end
Dec 16, 2015(actual)