Back to projects

Continuity of the Trans Canada Trail and the SNQ

Denholm, Quebec

completeRecreationNRT
Federal contribution
$50,000
Federal share46%

of $109.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2016
2016
Built

Approved 12 months before the announcement.

Program
National Recreational Trails Program
Construction start
Apr 7, 2015(actual)
Construction end
Dec 9, 2015(actual)

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51002 in the federal list. How to read these figures.