Capital Trails
Sainte-Brigitte-de-Laval, Quebec
Federal contribution
$37,765
Federal share33%
of $114.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 30, 2009
2010
Built
Approved 2 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Societe des sentiers de la region de la Capitale-Nationale du Québec
- Construction start
- May 26, 2009(actual)
- Construction end
- Mar 31, 2010(actual)