Expansion 2008-2011

Saint-Raymond, Quebec

completeActive TransportationNRT
Federal contribution
$57,258
Federal share18%

of $325.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 30, 2009
2010
Built

Approved 2 months before the announcement.

Program
National Recreational Trails Program
Ultimate recipient
Vallée Bras-du-Nord
Construction start
May 26, 2009(actual)
Construction end
Mar 31, 2010(actual)

Also in Saint-Raymond

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51087 in the federal list. How to read these figures.