Back to projects

Prairie and Pine Trail Enhancement/Safety

Norquay, Saskatchewan

completeRecreationNRT
Federal contribution
$15,000
Federal share50%

of $30.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2016
20152016
Built

Approved 16 months before the announcement.

Program
National Recreational Trails Program
Construction start
Nov 24, 2014(actual)
Construction end
Dec 8, 2015(actual)

Also in Norquay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51103 in the federal list. How to read these figures.