Back to projects

Study on integrating a structuring mode of transportation on Taschereau

Brossard, Quebec

completePublic TransitPTIF
Federal contribution
$222,664
Federal share50%

of $445.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2017
201820192020
Built

Approved 4 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Nov 30, 2017(actual)
Construction end
Mar 26, 2020(actual)