Road Rehabilitation - Resurfacing
Pinware, Newfoundland and Labrador
Federal contribution
$15.4M
$15,400,000
Federal share50%
of $30.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
201820192020202120222023
Built
Approved 5 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Construction start
- Apr 1, 2018(actual)
- Construction end
- Sep 30, 2023(actual)
Against the original forecast
- Construction start4 weeks earlyforecast May 1, 2018
- Construction end2 months earlyforecast Nov 30, 2023
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51392 in the federal list. How to read these figures.