Upgrade Sewage Pumping Stations No. 4 and No. 5
Dover, Newfoundland and Labrador
Federal contribution
$88,885
Federal share24%
of $376.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 1, 2017
20182019
Built
Approved 2 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Dover
- Construction start
- Feb 15, 2019(actual)
- Construction end
- Aug 30, 2019(actual)
Against the original forecast
- Construction start2 months lateforecast Dec 15, 2018
- Construction end4 months earlyforecast Dec 31, 2019
Also in Dover