Upgrade Sewage Pumping Stations No. 4 and No. 5

Dover, Newfoundland and Labrador

completeWastewaterSCF
Federal contribution
$88,885
Federal share24%

of $376.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2017
20182019
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Dover
Construction start
Feb 15, 2019(actual)
Construction end
Aug 30, 2019(actual)

Against the original forecast

  • Construction start2 months lateforecast Dec 15, 2018
  • Construction end4 months earlyforecast Dec 31, 2019