Hospital Pressure Reducing Valve Replacement

Happy Valley-Goose Bay, Newfoundland and Labrador

completeDrinking WaterSCF
Federal contribution
$16,623
Federal share33%

of $49.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2017
201820192020
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Dec 1, 2019(actual)
Construction end
Sep 30, 2020(actual)

Against the original forecast

  • Construction start6 months earlyforecast Jun 1, 2020
  • Construction end2 months earlyforecast Nov 30, 2020