Elgin Water Treatment System Upgrades

Grassland, Manitoba

completeDrinking WaterSCF
Federal contribution
$83,333
Federal share33%

of $250.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 9, 2017
201820192020202120222023
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Aug 20, 2021(actual)
Construction end
Dec 31, 2022(actual)

Against the original forecast

  • Construction start2.4 years lateforecast Apr 1, 2019
  • Construction end2 months lateforecast Oct 31, 2022