Elgin Water Treatment System Upgrades
Federal contribution
$83,333
Federal share33%
of $250.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 9, 2017
201820192020202120222023
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Rural Municipality of Grassland
- Construction start
- Aug 20, 2021(actual)
- Construction end
- Dec 31, 2022(actual)
Against the original forecast
- Construction start2.4 years lateforecast Apr 1, 2019
- Construction end2 months lateforecast Oct 31, 2022
Also in Grassland