Water Line Valve & Post/Flush Hydrant Installation - Various Locations and Pumphouse Upgrades
Marysvale, Newfoundland and Labrador
Federal contribution
$27,596
Federal share33%
of $83.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 1, 2017
2018
Built
Approved 2 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Local Service District of Marysvale
- Construction start
- May 16, 2018(actual)
- Construction end
- May 25, 2018(actual)
Against the original forecast
- Construction start6 weeks lateforecast Apr 1, 2018
- Construction end17 months earlyforecast Oct 31, 2019
Also in Marysvale