Water Line Valve & Post/Flush Hydrant Installation - Various Locations and Pumphouse Upgrades

Marysvale, Newfoundland and Labrador

completeDrinking WaterSCF
Federal contribution
$27,596
Federal share33%

of $83.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2017
2018
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
May 16, 2018(actual)
Construction end
May 25, 2018(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Apr 1, 2018
  • Construction end17 months earlyforecast Oct 31, 2019

Also in Marysvale

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51599 in the federal list. How to read these figures.