Winterton Recreation Center Upgrades

Winterton, Newfoundland and Labrador

completeRecreationSCF
Federal contribution
$67,264
Federal share30%

of $224.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2017
20182019202020212022
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Winterton
Construction start
Apr 26, 2021(actual)
Construction end
Apr 22, 2022(actual)

Against the original forecast

  • Construction start11 months earlyforecast Mar 25, 2022
  • Construction end6 weeks earlyforecast May 31, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51623 in the federal list. How to read these figures.