Pumphouse & wells replacement # 3 Yard -Wabana
Wabana, Newfoundland and Labrador
Federal contribution
$525,038
Federal share33%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 1, 2017
201820192020202120222023
Built
Approved 2 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Wabana
- Construction start
- Jan 20, 2021(actual)
- Construction end
- Jul 11, 2023(actual)
Against the original forecast
- Construction start2 months earlyforecast Apr 1, 2021
- Construction end3 months earlyforecast Sep 30, 2023
Also in Wabana
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51639 in the federal list. How to read these figures.