Street Upgrades and Paving 2017 - Cemetery Road
Little Bay East, Newfoundland and Labrador
Federal contribution
$29,156
Federal share25%
of $116.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 1, 2017
2018
Built
Approved 2 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Little Bay East
- Construction start
- Jun 30, 2018(actual)
- Construction end
- Sep 30, 2018(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Jul 20, 2018
- Construction end13 months earlyforecast Oct 31, 2019