Back to projects

Water and Sewer Upgrading Chapel's Cove & Fewer's Hill & Water Main Upgrades Conran’s Road

Harbour Main-Chapel's Cove-Lakeview, Newfoundland and Labrador

completeWastewaterSCF
Federal contribution
$453,753
Federal share33%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2017
20182019
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Aug 28, 2018(actual)
Construction end
Feb 26, 2019(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jul 1, 2018
  • Construction end10 months earlyforecast Dec 31, 2019

Also in Harbour Main-Chapel's Cove-Lakeview