Works to upgrade the Parc Georges-Painchaud dam

Lac-Saguay, Quebec

completeDisaster MitigationSCF
Federal contribution
$58,776
Federal share33%

of $176.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 10, 2017
201820192020
Built

Approved 4 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Municipality of Lac-Saguay
Construction start
Nov 21, 2018(actual)
Construction end
May 25, 2020(actual)

Against the original forecast

  • Construction start15 months lateforecast Aug 31, 2017
  • Construction end2.7 years lateforecast Sep 30, 2017

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51695 in the federal list. How to read these figures.