Chemin des Cypres improvement plan
Federal contribution
$3.7M
$3,739,864
Federal share32%
of $11.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 22, 2018
20182019202020212022
Built
Approved 5 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Regional County Municipality of Matawinie
- Construction start
- Jan 1, 2018(actual)
- Construction end
- May 20, 2022(actual)
Against the original forecast
- Construction start4 months earlyforecast Apr 30, 2018
- Construction end3.1 years lateforecast Mar 30, 2019
Also in Rawdon