Back to projects

Sewage Vacuum Truck

Wrigley, Northwest Territories

completeWastewaterSCF
Federal contribution
$125,000
Federal share70%

of $179.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 11, 2018
2018
Built

Approved 4 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Pehdzeh Ki First Nation
Construction start
Oct 1, 2017(actual)
Construction end
Apr 10, 2018(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Oct 31, 2017
  • Construction end2.6 years earlyforecast Dec 1, 2020

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51716 in the federal list. How to read these figures.