Purchasing of buses in 2018 (22)
Federal contribution
$9.4M
$9,437,483
Federal share50%
of $18.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 13, 2017
2017
Built
Approved 3 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Réseau de transport de Longueuil (RTL)
- Construction start
- Nov 11, 2016(actual)
- Construction end
- Dec 4, 2017(actual)
Also in Longueuil
- Acquisition of 98 Electric Buses$64.3M
- Construction of electrical infrastructure and a bus charging shelter at the Vieux-Longueuil Operations Center$34.8M
- Purchase of 29 buses in 2018 for Route 90$12.7M
- NCESH Phase 2: Opportunity File and Business File$10.8M
- Phase 1 Planning for the Construction of the Saint-Hubert Operations Center$8.6M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51733 in the federal list. How to read these figures.