Highway Rehabilitation Bundle
Federal contribution
$3.7M
$3,680,000
Federal share48%
of $7.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 3, 2019
20182019
Built
Approved 16 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Province of Saskatchewan
- Construction start
- May 25, 2018(actual)
- Construction end
- Oct 4, 2018(actual)
Against the original forecast
- Construction start3 months earlyforecast Aug 30, 2018
- Construction end4 weeks earlyforecast Oct 30, 2018
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51853 in the federal list. How to read these figures.