Dickson Dam Capacity Enhancement
Federal contribution
$6.9M
$6,884,607
Federal share50%
of $13.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 11, 2018
today
20182020202220242026
BuiltForecast
Approved 7 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Alberta Ministry of Transportation
- Construction start
- Oct 22, 2022(actual)
- Construction end
- Mar 31, 2027(forecast)
Against the original forecast
- Construction start4 months lateforecast Jul 1, 2022
Also in Red Deer County
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51873 in the federal list. How to read these figures.