Jensen Dam Rehabilitation
Federal contribution
$4.2M
$4,219,213
Federal share47%
of $9.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 11, 2018
2019202020212022
Built
Approved 5 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Alberta Ministry of Transportation
- Construction start
- Jul 7, 2020(actual)
- Construction end
- Apr 23, 2022(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Jul 31, 2020