Back to projects

National Highway System: PTH 16 (Yellowhead Highway) Rehabilitation

Portage la Prairie, Manitoba

completeHighways and RoadsNRP
Federal contribution
$18.0M
$18,000,000
Federal share41%

of $43.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2019
2018202020222024
Built

Approved 11 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Jan 11, 2020(actual)
Construction end
Nov 24, 2024(actual)

Against the original forecast

  • Construction start5 months earlyforecast Jun 1, 2020
  • Construction end6 months earlyforecast May 31, 2025