Construction of a reception center for municipal camping

Saint-Roch-de-Mékinac, Quebec

completeTourismSCF
Federal contribution
$61,703
Federal share33%

of $185.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 8, 2018
201820192020
Built

Approved 5 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Jun 1, 2018(actual)
Construction end
Jul 6, 2020(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Jun 30, 2018
  • Construction end21 months lateforecast Sep 29, 2018