Okanagan Rail Trail

Kelowna, British Columbia

underwayRecreationNRP
Federal contribution
$1.4M
$1,363,130
Federal share33%

of $4.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 12, 2018
2018202020222024
BuiltForecast
Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Apr 11, 2018(actual)
Construction end
Jun 30, 2025(forecast)

Against the original forecast

  • Construction start3 weeks earlyforecast Apr 30, 2018

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51906 in the federal list. How to read these figures.