Okanagan Rail Trail
Federal contribution
$1.4M
$1,363,130
Federal share33%
of $4.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 12, 2018
2018202020222024
BuiltForecast
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Regional District of North Okanagan
- Construction start
- Apr 11, 2018(actual)
- Construction end
- Jun 30, 2025(forecast)
Against the original forecast
- Construction start3 weeks earlyforecast Apr 30, 2018
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51906 in the federal list. How to read these figures.