Western Irrigation District - Cooperative Stormwater Management Initiative

Calgary, Alberta

underwayWastewaterNRP
Federal contribution
$2.1M
$2,067,500
Federal share31%

of $6.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 21, 2019
2019202120232025
BuiltForecast

Approved 5 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Ultimate recipient
Western Irrigation District
Construction start
Jan 31, 2021(actual)
Construction end
Mar 31, 2026(forecast)