Western Irrigation District - Cooperative Stormwater Management Initiative
Federal contribution
$2.1M
$2,067,500
Federal share31%
of $6.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 21, 2019
2019202120232025
BuiltForecast
Approved 5 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Western Irrigation District
- Construction start
- Jan 31, 2021(actual)
- Construction end
- Mar 31, 2026(forecast)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51921 in the federal list. How to read these figures.