Moosehide Village Solar PV
Tr'ondëk Hwëch'in First Nation, Yukon
Federal contribution
$246,839
Federal share62%
of $400.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 10, 2018
2019
Built
Approved 6 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Trondëk Hwëchin First Nation
- Construction start
- Aug 8, 2018(actual)
- Construction end
- Oct 31, 2019(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 1, 2018
- Construction end6 months lateforecast Apr 30, 2019
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51924 in the federal list. How to read these figures.