Restoration of the Ruisseau Rouge dam
Federal contribution
$94,549
Federal share33%
of $283.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 4, 2018
20182019202020212022
Built
Approved 3 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of L'Isle-aux-Coudres
- Construction start
- Jun 1, 2018(actual)
- Construction end
- Apr 27, 2022(actual)
Against the original forecast
- Construction start3 months lateforecast Mar 1, 2018
- Construction end3.8 years lateforecast Jun 28, 2018
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51939 in the federal list. How to read these figures.