Redevelopment of the Oscar-Ferland Library
Saint-Pierre-de-l'Île-d'Orléans, Quebec
Federal contribution
$135,532
Federal share33%
of $406.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 27, 2018
2018201920202021
Built
Approved 3 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of Saint-Pierre-de-l'Île-d'Orléans
- Construction start
- Sep 1, 2018(actual)
- Construction end
- Mar 18, 2021(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 1, 2018
- Construction end2.5 years lateforecast Sep 1, 2018
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51942 in the federal list. How to read these figures.