Construction of a permanent structure over the multifunctional ice rink
Federal contribution
$191,263
Federal share33%
of $573.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 7, 2018
20192020
Built
Approved 2 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of Frontenac
- Construction start
- Nov 1, 2018(actual)
- Construction end
- Mar 16, 2020(actual)
Against the original forecast
- Construction start7 months earlyforecast Jun 15, 2019
- Construction end2 months lateforecast Dec 31, 2019