Construction of a multisport surface

Rivière-Ouelle, Quebec

completeRecreationSCF
Federal contribution
$25,856
Federal share33%

of $77.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 30, 2018
2019
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Rivière-Ouelle
Construction start
Jul 15, 2018(actual)
Construction end
Sep 10, 2019(actual)

Against the original forecast

  • Construction start2 months lateforecast May 14, 2018
  • Construction end3 months lateforecast May 31, 2019

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51947 in the federal list. How to read these figures.