Repair of the masonry wall
Federal contribution
$798,430
Federal share33%
of $2.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 23, 2019
201920202021
Built
Approved 18 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Parish Municipality of Notre-Dame-des-Anges
- Construction start
- Feb 15, 2019(actual)
- Construction end
- May 12, 2021(actual)
Against the original forecast
- Construction start10 months lateforecast May 1, 2018
- Construction end2.6 years lateforecast Oct 1, 2018
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51948 in the federal list. How to read these figures.