2018 Collector Roads Bundle
Cornwall, Prince Edward Island
Federal contribution
$1.8M
$1,776,304
Federal share50%
of $3.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 5, 2018
2019202020212022
Built
Approved 5 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Government of Prince Edward Island
- Construction start
- May 30, 2018(actual)
- Construction end
- Jul 28, 2022(actual)
Against the original forecast
- Construction end8 months lateforecast Nov 30, 2021
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51951 in the federal list. How to read these figures.