Rehabilitation and Safety Improvement Work: Highways No. 3 & No. 4
Federal contribution
$8.1M
$8,093,250
Federal share50%
of $16.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 16, 2019
2019
Built
Approved 17 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Province of Saskatchewan
- Construction start
- Jul 23, 2018(actual)
- Construction end
- Oct 8, 2019(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Sep 1, 2018
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51955 in the federal list. How to read these figures.