Rehabilitation Work: Level of Service 1 Corridors

Bethune, Saskatchewan

completeHighways and RoadsNRP
Federal contribution
$34.1M
$34,141,950
Federal share50%

of $68.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 11, 2019
20192020202120222023
Built

Approved 9 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Ultimate recipient
Province of Saskatchewan
Construction start
Jan 1, 2019(actual)
Construction end
Jun 15, 2023(actual)

Against the original forecast

  • Construction start3 months lateforecast Oct 1, 2018
  • Construction end15 months earlyforecast Aug 31, 2024

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52030 in the federal list. How to read these figures.