Relocation of the municipal library of the Luceville sector

Sainte-Luce, Quebec

completeCultureSCF
Federal contribution
$54,880
Federal share33%

of $164.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 22, 2018
2019202020212022
Built

Approved 8 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Municipality of Sainte-Luce
Construction start
Sep 28, 2020(actual)
Construction end
Apr 20, 2022(actual)

Against the original forecast

  • Construction start2.3 years lateforecast Jun 25, 2018
  • Construction end3.5 years lateforecast Oct 5, 2018